Additional insured status is the single most requested, and most often missing, piece of a contractor's coverage. This is what the endorsements do, which ones matter on a construction job, and how to tell them apart.

Docket COIJ-26-0006November 13, 20263 min read

By The editors, COI Journal ·

The questionWhat is an additional insured endorsement like CG 20 10, and why does a construction project need it?

Key findings

  1. An additional insured endorsement extends a contractor's general liability policy to protect someone else, usually the GC and the owner, for liability caused by the contractor's work.
  2. CG 20 10 covers ongoing operations. CG 20 37 covers completed operations. A project usually needs both.
  3. Automatic, or blanket, forms grant status to anyone the contractor agreed in a written contract to add, so the contract wording becomes part of the coverage.
  4. Since the 2013 ISO edition, additional insured coverage generally can't be broader than the contract requires. A weak requirement makes for weak coverage.

What the endorsement does

A contractor's general liability policy protects the contractor. An additional insured endorsement extends that protection to someone else: on a construction job, usually the general contractor, the owner and sometimes the architect or lender.

The point is to keep the GC's own policy out of claims caused by the trade's work. If a passerby is hurt by a trade's falling materials and sues everyone on the job, the GC wants to be defended by the trade's carrier, not its own.

That only works if the endorsement exists. The ACORD 25 says so in its own words: if the certificate holder is an additional insured, the policy must have additional insured provisions or be endorsed. The Y in the ADDL INSD column is not the endorsement.

The forms that matter on a construction job

ISO, which writes the standard policy forms most carriers start from, publishes dozens of additional insured endorsements. On construction projects, a handful do most of the work.

  • CG 20 10, ongoing operations, scheduled. Covers the people named in its schedule for liability arising during the contractor's ongoing work.
  • CG 20 37, completed operations, scheduled. Covers the people named in its schedule for liability that arises after the work is finished. As the Construction Defect Journal noted, it requires each additional insured to be listed in its schedule.
  • CG 20 33 and CG 20 38, ongoing operations, automatic. Grant status to parties the contractor agreed in a written construction contract to add, without naming each one. CG 20 38 reaches further up the contract chain, to parties the contractor's direct client is required to add.
  • CG 20 39 and CG 20 40, completed operations, automatic. Added in ISO's 2019 filing as the completed operations counterparts to CG 20 33 and CG 20 38, according to IIABA.

Carriers also write their own versions under their own form numbers. When the endorsement isn't an ISO form, read what it says rather than assuming it matches one.

Ongoing and completed: you usually need both

The most expensive mistake on this list is having one without the other. An ongoing operations endorsement stops responding when the work is done. Construction defect and many injury claims arrive later. See completed operations.

If the contract requires completed operations coverage for a number of years after completion, the endorsement has to exist and the contractor's policy has to keep being renewed with it for that whole time.

Scheduled or automatic

A scheduled form names you. An automatic form describes you, usually as anyone the contractor has agreed in a written contract to add.

Automatic forms save paperwork and avoid missed names. They also make the subcontract part of the coverage. If the contract wasn't signed before the work started, wasn't in writing, or doesn't require additional insured status in the right terms, an automatic endorsement may not reach you.

The contract sets the ceiling

ISO's April 2013 edition changed how far additional insured coverage reaches. The new language says coverage "will not be broader than that which you are required by the contract or agreement to provide," IRMI's Gregory Podolak wrote, and ties the limits available to the additional insured to the amount the contract requires, whichever is less.

The practical effect: what your subcontract asks for is now, in large part, what you get. A requirement that says only "name GC as additional insured" may buy less than one that names the scope, the duration, and both ongoing and completed operations.

What to check

  1. Ask for the endorsement itself, with its form number and edition date.
  2. Confirm it covers both ongoing and completed operations, or that you have one of each.
  3. On a scheduled form, confirm your exact legal name is in the schedule. On an automatic form, confirm your subcontract's wording and signature date fit its conditions.
  4. Confirm the limits available meet what your contract requires.
  5. Check again at renewal. Endorsements don't automatically carry over.

See additional insured in the COI Dictionary, and our brief on how the ISO editions changed.

How we wrote this

This paper draws on the ACORD 25 form and published analysis of ISO's additional insured endorsements by IRMI, the Independent Insurance Agents & Brokers of America and the Construction Defect Journal. Carriers also file their own forms, which can differ. General information, not legal or insurance advice.

Sources

  1. Today's Additional Insured Endorsements: Revisiting the Impact of ISO Form Changes, IRMI, Gregory Podolak, March 1, 2015
  2. Chris Boggs on the 2019 ISO additional insured endorsements, Independent Insurance Agents & Brokers of America, Chris Boggs, December 20, 2019
  3. The 2019 ISO Forms: Additions, Revisions, and Pitfalls, Construction Defect Journal, Saxe Doernberger & Vita, February 24, 2020
  4. ACORD 25 Certificate of Liability Insurance (2025/12), as posted by the New York State Department of Financial Services, ACORD / NY DFS

General information, not legal or insurance advice. Read your contracts and policies with your broker or attorney. COI Journal is published by Forsured, which sells construction insurance compliance software. How we keep editorial separate.

More from Reports

R-13White paperResource Center

What to require from any COI tool: a vendor-neutral specification

We don't rank software. But we can tell you what to ask for. This is a specification any COI tool, service or spreadsheet process can be measured against, with a way to test each line yourself.

Docket COIJ-26-0014November 13, 20262 min read

R-10White paperResource Center

Can AI review a COI? What machines do well, and where people stay in the loop

AI is good at reading documents and comparing them with rules. Certificate review is mostly that. But some calls need a person, and some questions can't be answered from the documents at all.

Docket COIJ-26-0011November 13, 20262 min read

R-06White paperResource Center

When a contractor's coverage lapses mid-project: the exposure and the playbook

Policies expire, get cancelled for nonpayment, or come back at renewal without the endorsements you asked for. The certificate in your file won't tell you. Here is what's at stake and what to do.

Docket COIJ-26-0007November 13, 20262 min read

New reports in The COI Digest

Get The COI Digest

Worth Reading, our picks of the week's best construction insurance reporting, plus one term and one gap. Tuesday mornings, five minutes.

By subscribing, you agree to Forsured's Terms of Service and Privacy Policy. Unsubscribe from any email.

From our publisher

Check a contractor COI against your project requirements, free.

Forsured, which publishes COI Journal, will read one project's requirements and a contractor COI or two, and show you every gap it finds.